Meralco Net Metering: How It Actually Works (Philippines, 2026)

Published 2026-07-05 · Updated 2026-10-03 · By TipidKuryente Editorial · Calculator figures use the sourced dataset

One number decides whether a net-metered solar system is the right size, and it’s the one most people get wrong, a few salesmen included. So that’s where this guide starts.

Exports do NOT earn the retail rate

You pay Meralco about ₱15.55 per kWh, all-in. When your roof sends extra power back to the grid, the credit you get is Meralco’s generation charge: ₱10.6349 per kWh in November 2026, and it changes when that charge does each month. This comes from the ERC’s amended net-metering rules of 2025 (Resolution No. 15, Series of 2025), under which exports earn the utility’s blended generation charge without the other adjustments. Outside Meralco, it’s your own utility’s generation charge.

Why the gap? Your retail rate is generation plus transmission, distribution, system loss and taxes. The export credit covers only the generation part, because Meralco still has to pay for the wires that bring power back to you at night. That’s fair enough, but it means:

A kWh you use is worth about 1.5 kWh you sell.

Where each kWh goes under net metering, and what it is worthBy day, solar you use at home saves ₱15.55 per kWh, and solar you export is credited ₱10.63 per kWh. At night, power you buy from Meralco costs ₱15.55 per kWh.BY DAYSolar you use at homesaves ₱15.55 for every kWhSolar you exportcredited ₱10.63 per kWhAT NIGHTPower you buy from Meralcocosts ₱15.55 per kWh
The export credit covers only the generation slice, so the same kWh is worth about 46% more used at home than sold back.

Size everything around that. A system matched to what you use in the daytime beats a bigger one that exports its extra at ₱10.63. If a proposal justifies more panels “because net metering pays for them,” remember net metering pays ₱10.63, not ₱15.55. The payback calculator shows exactly what that does to the break-even year.

How the credits actually flow

A bi-directional meter counts what goes out, and the peso credit shows up on your next bill to offset your charges. It never turns into cash. If you pile up a big credit, you’ve basically lent money to your own future bills at zero interest, which is one more reason not to oversize.

The paperwork

Net metering was created by RA 9513, the Renewable Energy Act, and the program does work. Systems up to 100 kW qualify, far bigger than anything on a house. Here’s the order things happen in:

  1. Your installer files the application with your system specs.
  2. A distribution impact study: for house-scale systems, quick or waived.
  3. Meter swap to bi-directional, one-time fee.
  4. Sign the connection agreement; credits start next billing cycle.

On paper that takes a few weeks. In practice it has taken months, and it varies a lot from city to city. The rules changed in April 2026, though. A DOE reform under Executive Order No. 110 cut the time a distribution utility has to decide from 20 working days to 10, with no extensions. It limited LGU electrical permits to 3 working days, and an application now counts as deemed granted if an agency misses its deadline. So if your utility is still sitting on a complete application after day 10, it’s breaking a rule, not just being slow, and you can take it to the ERC.

Several installer blogs get two details wrong. The 100 kW personal-use cap did not change, and the old deadline was 20 working days, not the 45 some guides claim. That’s how both Philstar and Power Philippines reported it.

What Meralco asks for

Meralco’s application page lists what you need to file, usually through your installer:

  1. The Net-Metering Application Form for Solar PV Systems. Add the Annex Sheet if your system uses more than one model of panel, inverter or battery.
  2. A Certificate of Final Electrical Inspection (CFEI) from your city or municipal hall.
  3. The amended Net-Metering Agreement, signed. It doesn’t have to be notarized, and e-signatures are fine.
  4. Proof that you paid the ERC’s ₱1,500 Certificate of Compliance fee, paid through the ERC and Landbank’s Link.BizPortal, by manager’s check or in cash.

On top of what the installer charges, there’s that ₱1,500, plus the difference in cost for the bi-directional meter, which can’t be more than ₱3,000 for a home. A distribution asset study fee only applies if Meralco’s review finds that the line to your house needs an upgrade. If you skip the optional Renewable Energy Certificate meter, Meralco asks for a notarized affidavit and waiver.

One limit surprises people: how much solar Meralco will connect depends on the transformer that serves your street, from 7 kW to 38 kW for a home, well under the 100 kW cap. Have your installer check it before you settle on a size.

A good installer handles all of this. Make sure it’s in the quote before you sign (what belongs in a quote).

How long it really takes

The 10-day rule is new, and what owners actually go through hasn’t caught up yet. These are the timelines people posted on Reddit between July 2025 and August 2026, each linked to the post:

ReportedWhereWhat they said
Aug 2026BicolLGU inspection certificate (CFEI) in 3 days, utility inspection 2 weeks, meter a week later; ₱5,000 spent in all, of which ₱500 to the LGU and ₱1,500 to the ERC (u/VerityOnce)
Aug 2026MalabonFiled it personally; everything paid came to under ₱10,000 (u/bampie)
Jun 2026not statedOne year pending (u/Silent_Hero7)
May 2026MeralcoOne year pending, papers stuck at system encoding (u/ajsavestheworld)
May 2026not statedStill waiting, in the third year (u/ImportantGuide)
May 2026not statedActivated after six months, after following up and notarizing the papers personally (u/PawisangItlog)
May 2026not statedSix months, installer handled everything (u/Powerful_Resist_5625)
Mar 2026AEC, PampangaQuick meter installation, no problems; installer did the processing (u/SafelyLandedMoon)
Nov 2025Meralco, San PedroNearly a year to approval; the installer’s part took two months (u/Fatal1s)
Oct 2025PampangaNine months (u/dhaybrave)
Aug 2025LagunaSeven months (u/KeyBunch2761)
Jul 2025Meralco, AlabangAbout six months (u/QuarterAdorable4083)
Jul 2025Meralco, Indang and ParañaqueAn installer: 12 months for a client who filed alone; 4 months once it took over an application stalled for 18 (u/ajsc86)

Three things stand out:

  1. Six to twelve months was normal in Meralco’s area, and some applications filed before April 2026 are still waiting. If yours is complete and the utility has gone past 10 working days since the reform, it’s breaking the rule, and you can take it to the ERC.
  2. The utility’s own fees are small. Owners who filed themselves reported about ₱5,000 and under ₱10,000. Installers charge far more to do it for you: one quote on r/SolarPH added ₱20,000 for net-metering processing, another ₱65,000. Check whether your quote includes it, and how much it adds.
  3. Following up helps. In the faster cases someone kept chasing the paperwork, like the owner who had the papers notarized and pushed them through personally, or the installer that took over a stalled file. A complete application that nobody follows up can just sit there.

Is it worth it?

Yes. The credit is about 68% of what a kWh you use yourself saves, but without net metering that power would go to the grid for nothing, and the meter is a one-time cost. Size the system for what you use during the day, treat the ₱10.63 as a bonus, and be wary of anyone who sizes it the other way around.