ERC Suspends the Reserve Power Market That Added ₱1.29/kWh to Visayas Bills

2026-10-18 · Philippines · By TipidKuryente Editorial

What it does to your bill: No bill changes yet, since the order only covers charges going forward, but it targets the single biggest spot-market cost behind high Visayas rates, and NGCP now has 30 days to show how it will cover reserves without that spot-market premium.

The Energy Regulatory Commission has suspended commercial dispatch and settlement of the Reserve Market inside the Wholesale Electricity Spot Market (WESM), the mechanism the National Grid Corporation of the Philippines (NGCP) uses to buy backup power on short notice when its long-term contracts fall short. The order, approved October 8 under ERC Case No. 2023-002 RC with the Department of Energy’s concurrence, took effect as soon as the Philippine Electricity Market Corp. (PEMC), the Independent Electricity Market Operator of the Philippines (IEMOP), and NGCP received it.

Why the Visayas is the target

NGCP covers its reserve requirement two ways: long-term Ancillary Service Procurement Agreements (ASPAs) at regulated rates, or ad hoc purchases on the Reserve Market at whatever price generators name. In the Visayas, the gap between those two prices has been enormous.

2025 costEffect on rates
Reserve Market (spot)₱19.57 billion₱1.29/kWh
ASPAs (long-term contracts)₱1.69 billion₱0.02/kWh

Luzon showed the same pattern at a smaller scale: ₱24.53 billion in spot reserve purchases against ₱12.75 billion in contracted services. The ERC’s move cuts off the far more expensive of the two routes.

What happens next

While the suspension holds, NGCP has to source reserves from its existing ASPAs or other bilateral contracts. The ERC gave NGCP 30 days to submit a region-by-region assessment of which reserve requirements aren’t covered by current contracts and how it plans to fill those gaps, through competitive selection first and direct negotiation only where allowed. Separately, NGCP, PEMC and IEMOP have six months to jointly propose a redesign of the reserve market itself. NGCP was also told to start publishing its reserve-demand forecasts, so battery-storage developers and other prospective suppliers can bid on filling them.

Outlets differ on how permanent this is: some describe the suspension as indefinite, pending that redesign; others call it temporary, tied to the same 30- and 180-day deadlines. Either way, no new reserve-market charges accrue until the ERC says otherwise.

What it means for your bill

Nothing changes on a bill you’ve already received or will receive for charges already incurred; the order only stops new Reserve Market charges from building up going forward. But the ₱1.29/kWh the spot reserve market added to 2025 Visayas rates is exactly the kind of charge that has kept pushing co-op rates in Biliran, Leyte, and Cebu well above Meralco’s, as our Visayas rate breakdown lays out. Whether this actually lowers your rate depends on what NGCP’s new 30-day contracts cost compared to the spot prices they replace, and that figure isn’t public yet.