Solar and Storage Group Tells ERC Its Visayas Reserve Market Freeze Could Backfire
What it does to your bill: No bill changes from this filing alone, but it's a direct industry challenge to the fix regulators chose for high Visayas reserve costs, arguing the freeze could slow down the battery storage projects the grid needs to cut future red alerts.
The Philippine Solar and Storage Energy Alliance (PSSEA), an industry group representing solar and battery developers, has filed a position paper asking the Energy Regulatory Commission (ERC) to immediately resume commercial dispatch and settlement of the Reserve Market across Luzon, the Visayas, and Mindanao. The filing is a direct pushback against the ERC’s own October 8 order that suspended that same market under ERC Case No. 2023-002 RC to curb the high ancillary-service costs it had been adding to Visayas bills.
Why PSSEA says the freeze could backfire
PSSEA’s argument is that halting the Reserve Market doesn’t fix what’s actually driving up Visayas costs. The group says the suspension “creates further market distortions” instead of encouraging investment in the additional reserve capacity the region needs, and that it could discourage investment in battery storage and other critical power infrastructure at the exact moment the Visayas needs more of it. PSSEA Chair Tetchi Capellan summed up the group’s position: “The solution to high electricity costs affecting Visayas is to address the underlying supply and flexibility constraints in the region.”
As an alternative, PSSEA is pushing for competitive forward contracting of battery storage, which it describes as immediately deployable and capable of responding fast when a plant trips. The group also cited IEMOP data showing contingency-reserve prices already fell 24.8% in July as reserve volumes rose, arguing that’s evidence the market was already correcting itself without a suspension.
What the suspension actually did
| Detail | |
|---|---|
| Order | ERC Case No. 2023-002 RC, approved October 8 |
| What it suspended | Commercial dispatch and settlement of WESM’s Reserve Market |
| 2025 Visayas Reserve Market cost | ₱19.57 billion (₱1.29/kWh) |
| 2025 Visayas ASPA (contracted) cost | ₱1.69 billion (₱0.02/kWh) |
| PSSEA’s ask | Immediate resumption, paired with competitive battery contracting |
That ₱1.29-per-kWh gap between spot reserve purchases and long-term contracts is what the ERC was trying to close. PSSEA isn’t disputing that the spot market got expensive; it’s disputing the fix, arguing that NGCP should be locking in cheaper contracted reserves, like the EAUC battery deal in Mactan, Cebu the ERC provisionally approved around the same time, rather than freezing the market developers need to sell into in the first place.
What it means for your bill
Nothing changes on a Visayas electric bill from this filing. It’s a regulatory dispute playing out before any of it reaches a meter: PSSEA wants the ERC to let the Reserve Market keep running while separately pushing NGCP toward more contracts like the Mactan battery deal, instead of freezing the market altogether. Whether the ERC adjusts its order will matter for how fast the battery backup DOE says could cut Visayas alerts in half actually gets built. For now, our Visayas rate breakdown still reflects the current suspension as the operative rule.